Mechanical Fabrication & Erection Works of 60 KTPA Phase-2

Client:

LCI Soda Ash Business Khewra

Contractor:

PREFAB SERVICES PVT. LTD

Duration:

14 Months

Total Cost of Project :

380 million

Project Discription:

Steel Structure 1488 Ton, CS/SS Piping 113, 400 Dia Inch, CI Piping 252 Ton, Kiln # 09 238 Ton, Kiln # 09 (Refractory) 900 Ton, Counter Flow Cooling Tower 3300 m3/Hr, Sand Blasting 1920 Ton, Painting 1920 Ton.